Machining Facilities

  • * Floor Type Horizontal Boring Machine : Make: WMW Germany, Spindle Dia: 160mm Rotary Table Size: 2300mmx2030mm.
  • * Precision Centre Lathe: Make: WMW Germany, Centre to Centre Distance: 6000 mm, Swing Dia: 1050 mm.
  • * Other Machines: Radial Drilling machine, Magnetic Drill machine, Slotting Machine, Shaper Machine, Surface Grinder, Horizontal Milling Machine & Portable boring machine.
  • * Fabrication Facilities: Hydraulic Press (150 MT), Plate bending and rolling machine (25 mm), Plasma Cutting Machine (68 mm plate cutting), welding Machines - 30 Nos.
  • * Stress Relieving Furnace: Can accommodate job of size 5000mmx5000mm x 2.5 mm Height). 40 MT capacity. Digitally controlled functioning.

Fabrication Facilities

  • * Plate bending machine : Max. thickness : 25 mm, Max width : 2250 mm
  • * Hydraulic Press (500 Ton)
  • * TIG welding set (Ador make)
  • * MIG welding sets (Ador make) : 4 Nos.
  • * PUG machines (ESAB) : 4 Nos.
  • * Shot/Sand Blasting machine (NESCO)
  • * Plasma Cutting m/c (GERRARD) Max thickness for SS plate 25 mm.
  • * Hand operated gas cutters : 5 Nos.
  • * Gauzing M/c up to 1000 Amp. (Ador)
  • * Welding rectifiers & generators up to 600 Amp : 20 Nos.
  • * Electrodes Pre Heating Ovens : 12 Nos.
  • * Electrodes Holding Ovens : 5 Nos.



Material Handling Facilities

EOT Cranes up to 40 Ton capacity 5 Nos.
Jib Crane 3 Ton capacity 1 No
Gantry Crane 5 Ton capacity 1 No
Hydra Crane 9 Ton Capacity 1 No
Fork Lifter 5 Ton Capacity 1 No


List Of Major Hydro – Electric Projects Executed Successfully

Sl. No. Proj Name Location Power House Capacity  Year of Execution Order value in USD
1 Mohammadpur, UJVNL (RMU of existing Power House) Uttarakhand (India) 9.3 MW 2013 around 10 Million $
2 Varzob-I HEP (RMU of existing Power House) Tazikistan 9.5 MW 2013 0.53 Million $
3 Sobla** (New Project) Uttarakhand (India) 8 MW 2013 1.93 Million $
4 Ganderbal (RMU of existing Power House) Jammu & Kashmir (India) 4.5 MW 2020 0.88 Million $
5 Galogi (RMU of existing Power House) Uttarakhand (India) 0.5 MW 2018 0.52 Million $
6 Kaliganga-I (New Project) Uttarakhand (India) 4 MW 2013 1.3 Million $
7 Pilangad (Civil Works) Uttarakhand (India) 2.25 MW 2018 1.3 Million $
1. ** During Commissioning this project got washed away due to natural calamity.
2. RMU means Renovation, Modernization and Upgradation of rated capacity.
3. HEP means Hydro-Electric Project


List of Major Hydro-Electric Projects that are Under Execution

Sl. No. Proj Name Location Power House Capacity  Year of Execution Order value in USD
1 Suringad, UJVNL (New Project including Construction of Power house) Uttarakhand (India) 5 MW 2021 2.34 Million $
2 Kaliganga-I, UJVNL (New project) Uttarakhand (India) 4.5 MW 2021 1.46 Million $
3 Budhkalan, HPGCL (RMU of Existing Power House) Haryana (India) 8 MW 2021 0.21 Million $
4 Chhirkila, UREDA (RMU of Existing Power House) Uttarakhand (India) 1.5 MW 2021 0.73 Million $
3 Dhalipur, UJVNL (RMU of 3 Units of Existing Power House) Uttarakhand (India) 3 x 17 1st Unit:2021
2nd Unit:2022
3rd Unit:2023
66 Million $